HAVE BECOME IMMENSELY POPULAR, BUT IT TAKES TIME TO GET THE STREETS READY TO HAVE THEM APPLIED.STREETS ARE SELECTED BASED ON THE AMOUNT OF FUNDS AVAILABLE AND HOW THAT PAVEMENT MOST RECENTLY SCORED.
ONCE STREETS ARE CHOSEN, WE LOOK AT HOW MUCH CONCRETE WORK IS NEEDED, WHICH UTILITIES ARE INVOLVED, AND WHAT OTHER PROJECTS CONFLICT WITH THE OVERLAY.
THIS PROCESS CAN TAKE UP TO TWO YEARS DEPENDING ON THE AMOUNT OF WORK THAT NEEDS TO BE DONE.
ONCE THE CONCRETE IS FIXED, AN ASPHALT OVERLAY IS INSTALLED THE FOLLOWING SPRING OR SUMMER.
LET'S HAVE A LOOK AT THE ASPHALT WORK YOU'LL BE SEEING THIS SUMMER.
FIRST, WE WILL BE COMPLETING AN OVERLAY FROM LAST YEAR THAT GOT DELAYED DUE TO THE WEATHER.
THAT WORK STARTS UP AGAIN THIS SPRING ON HEDGE OAKS ROAD FROM CUSTER ROAD TO PRESTON ROAD.
NEXT, OVERLAY OPERATIONS MOVE TO THE STRETCH OF MIDWAY ROAD FROM SPRING CREEK PARKWAY TO PARK BOULEVARD.
WEST PARKER ROAD IS ALSO ON THE LIST AND THE OVERLAY WILL BE APPLIED FROM PARKWOOD BOULEVARD TO PRESTON ROAD.
THE OVERLAY WORK ON INDEPENDENCE PARKWAY WILL RUN FROM SPRING CREEK PARKWAY TO STATE HIGHWAY 1 21.
IF WEATHER PERMITS AND TEMPERATURES STAY ABOVE 60 DEGREES, WE WILL GET TO ALMA DRIVE FROM PARKER ROAD TO HEDGE OAKS ROAD, AND THIS WILL BE THE LAST OVERLAY FOR 2025.
ALL THESE PROJECTS ARE EXPECTED TO BE COMPLETED THIS SUMMER IN PREPARATION FOR FUTURE OVERLAYS.
WE WILL BE PREPARING CONCRETE ON FIVE ROAD SECTIONS ALONG COMMUNICATIONS PARKWAY, MCDERMOTT ROAD LEGACY DRIVE, CUSTER ROAD, PARKER ROAD, AND COY ROAD.
AS YOU CAN SEE, THERE'S QUITE A BIT OF WORK SCHEDULED FOR THIS YEAR.
THANK YOU FOR YOUR PATIENCE AS WE CONTINUE TO IMPROVE OUR CITY FOR EVERYONE TO ENJOY.